Deep Yellow enters Technology Licence Agreement
Perth, Sep 12, 2016 AEST (ABN Newswire) - Advanced stage uranium explorer Deep Yellow Limited (ASX:DYL) (DYLLF:OTCMKTS) is pleased to announce that it has entered into a binding Technology Licence Agreement ("TLA") with Marenica Energy Ltd ("MEY") (ASX:MEY) (MARXF:OTCMKTS) giving it the option to use MEY's U-pgrade(TM) process on its Tumas Project located in Namibia. The agreement is the culmination of over three years of engagement with MEY and allows DYL to rapidly move into the next phase of project development, being further metallurgical testwork, a resource expansion drilling program and a fast track feasibility study program.
KEY POINTS
- Deep Yellow Ltd ("DYL") and Marenica Energy Ltd ("MEY") have executed a binding Technology Licence Agreement for the application of the U-pgrade(TM) process on the Company's Tumas Project in Namibia.
- The commercialisation agreement follows the recent conclusion of a successful metallurgical testwork program and aims to share the economic benefit of the resource/technology combination 75/25 (DYL/MEY) under various conditions.
- The testwork program demonstrated that processing Tumas ore through the U-pgrade(TM) process has the potential to reject up to 98% of the mass whilst recovering over 82% of the uranium, thus presenting the potential to dramatically reduce both capital and operating costs and enabling it to be developed at a lower uranium incentive price.
- The companies are already in an advanced stage of planning a fast track feasibility study which would include metallurgical variability testwork and a resource expansion drilling program.
The TLA aims to share the economic benefit of the combination of the resource and technology in a ratio of 75/25 (DYL/ MEY) and comprises initially a series of lump sum payments and then ongoing fees once the U-pgradeTM plant has met specific performance indicators. The ongoing fee varies with sales price and is nominal if uranium is sold at a price below US$50/lb and is capped at US$4.80/lb if the uranium price received exceeds US$80/lb. As an example, the fee will be US$2.60/lb at US$60/lb.
"We have been carefully managing numerous parallel elements in regard to the Tumas Project and have long been confident that those efforts would soon be rewarded" DYL's Managing Director Greg Cochran said. "This landmark agreement giving us access to the U-pgrade(TM) process will enable us to accelerate the Project's development leveraging off the potential to capture significant cost benefits as a result of the application of this technology."
Key Terms of the TLA
- The agreement gives DYL the option to use MEY's U-pgrade(TM) process in a plant sourcing ore from any of the Company's Namibian EPLs, giving it full operational flexibility;
- The focus will be on the delivery of the relatively advanced Tumas Project;
- DYL will make three lump sum payments which are back-loaded and triggered on the delivery of specific project outcomes during the feasibility, development and commissioning phases;
- Ongoing Licence Fees (which are considered fair for both parties) range from 2% to 6% of price received resulting in a 75/25 (DYL/MEY) sharing of the Tumas Project's NPV;
- The plant must achieve specific performance indicators and there is a detailed and prescriptive process in order for MEY to receive its Licence Fees;
- MEY personnel will be an integral part of the Tumas project development team;
- DYL will fund all project development expenditure including costs associated with U-pgrade(TM) testwork.
The Tumas Project
The Tumas palaeochannel straddles the Company's two wholly owned EPLs (3496 and 3497 - See Figures 1 and 2 in link below) and is divided into three zones. The Tumas deposit has a current 2004 JORC Compliant Resource of 14.8Mt at 366 ppm U3O8 for 11.9 Mlbs U3O8 (see Appendix 1 in link below for JORC Resource and Competent Persons' Statement). However, the palaeochannels have extensive upside potential as demonstrated by DYL's recent exploration success. (See ASX release dated 16 July 2015 titled "Enhanced Palaeochannel Prospectivity" for more information.)
An infill drilling program completed within Zone 1 of the Tumas resource at the end of 2014 and a sophisticated geophysical modelling exercise in 2015 provided confidence in the Tumas deposit and its extended palaeochannel. This enabled the decision to proceed with MEY and with the first phase metallurgical testwork program. Bulk samples were excavated from the infill drilling area in December 2015 and January 2016 and sent to Perth for this purpose.
The metallurgical testwork program was successfully completed on time at the end of June 2016 and the final report has been received from Marenica and is being reviewed. The final results reflect and reinforce the interim results achieved (see DYL ASX releases dated 20 May, 31 May and 1 July 2016) which gave DYL the confidence to finalise the TLA.
The interim results determined that more than 95% of the carbonate minerals could be removed with a loss of less than 5% of the uranium whilst the de-sliming step rejected ~27% of the mass as fine particulate material. These results demonstrated that the critical carbonate and de-slime removal steps of the U-pgrade(TM) process work on the Tumas samples provided and that use of the process would enable a significant reduction in the mass being handled with a minor loss of uranium, allowing the upgrading of uranium into a low mass concentrate.
In fact the results indicated that a concentrate containing less than 3% of the ore feed mass grading greater than 13,000 ppm U3O8 and containing greater than 82% of the uranium can be generated from the Tumas samples by MEY's U-pgrade(TM) process.
This presents two project options for Tumas - the final concentrate produced by U-pgrade(TM) could be processed on site using conventional acid leaching and refining technology to produce yellowcake. Alternatively the concentrate produced could be safely and cost-effectively transported to a third party for final processing (see Figure 3 in link below).
Marenica U-pgrade(TM) Technology
After extensive testwork (especially on Namibian calcretes) MEY's U-pgrade(TM) technology has been shown to improve the processing properties of surficial calcrete uranium ores. Both MEY and DYL believe that this improvement has the potential to dramatically reduce the capital and operating cost for processing these types of ores. (Figure 3 shows the various steps and the effectiveness of the technology's application.)
Next Steps
DYL and MEY have been working together and are already well advanced in planning the next stages of the Tumas Project. The final results of the Metallurgical Testwork Program and a Tumas Resource Update will be released shortly as well as a detailed Project Schedule. The Project Schedule will consider all activities up to and including the completion of a definitive feasibility study and is likely to include:
- A phased 600 metre triple tube geological and metallurgical diamond drilling program (HQ and PQ diameter) is being planned which will inform and generate core for the second phase metallurgical testwork program.
- An extensive metallurgical variability testwork program once again conducted under the supervision of MEY at Perth-based laboratories.
- An accelerated prefeasibility study conducted in parallel with the metallurgical testwork program.
- Updating the Scoping SEIA Report which was completed and submitted to the Namibian Ministry of the Environment and Tourism in 2013.
- A resource expansion drilling program and concomitant resource update/s.
- A pilot plant test program (only if required) and a definitive feasibility study.
As a result of the work already completed and assuming that similar results are achieved in the next phase of metallurgical testwork DYL is now confident that the Tumas Project is ideally positioned to become Namibia's next uranium mine.
DYL and MEY are looking forward with great optimism to making this a reality.
To view tables and figures, please visit:
http://abnnewswire.net/lnk/U5IK7IV7
About Deep Yellow Limited
Deep Yellow Limited (ASX:DYL) (OTCMKTS:DYLLF) is successfully progressing a dual-pillar growth strategy to establish a globally diversified, Tier-1 uranium company to produce 10+Mlb p.a.
The Company's portfolio contains the largest uranium resource base of any ASX-listed company and its projects provide geographic and development diversity. Deep Yellow is the only ASX company with two advanced projects - flagship Tumas, Namibia (Final Investment Decision expected in 1H/CY24) and MRP, Western Australia (advancing through revised DFS), both located in Tier-1 uranium jurisdictions.
Deep Yellow is well-positioned for further growth through development of its highly prospective exploration portfolio - ARP, Northern Territory and Omahola, Namibia with ongoing M&A focused on high-quality assets should opportunities arise that best fit the Company's strategy.
Led by a best-in-class team, who are proven uranium mine builders and operators, the Company is advancing its growth strategy at a time when the need for nuclear energy is becoming the only viable option in the mid-to-long term to provide baseload power supply and achieve zero emission targets.
Importantly, Deep Yellow is on track to becoming a reliable and long-term uranium producer, able to provide production optionality, security of supply and geographic diversity.
| ||
|