Perth, July 29, 2016 AEST (ABN Newswire) - Goldphyre Resources (googlechartASX:GPH) is pleased to report another very successful quarter, with several targets achieved. The Company is very focused on capturing the opportunity that currently exists in the Australian potash space, by being the first to develop its brine SOP project. To that end, Goldphyre is deliberately maintaining an achievable sized footprint and exploring all options to identify the fastest route to development, with the most efficient CAPEX spend.

Goldphyre achieves first strategic milestone

Maiden JORC Resource comprising 10.5Mt of extractable, highgrade 9.03kg/m3 Sulphate of Potash (SOP) within larger 18.4Mt extractable SOP Resource.

Highlights

- Successful air core and diamond drilling campaign intersected essential, highly porous basal sand layer in Lake Wells Potash Project palaeochannel - without sand layers in an aquifer, brine abstraction is very difficult

- Upper sand layers were intersected leading to the identification of a previously unconsidered upper aquifer

- Further high-grade assays were recorded through the quarter

- Maiden JORC Mineral Resource Estimate was published

- Using total porosity1 (for industry comparison purposes only), total in-situ Inferred Mineral Resource Estimate of 70 million tonnes of SOP at 8.05 kg/m3 including:

High-grade zone: 40 Mt of SOP at 9.03 kg/m3

- Using specific yield2 (drainable porosity), Inferred Mineral Resource Estimate of 18.4 million tonnes of SOP at 8.05 kg/m3 including:

High-grade zone: 10.5 Mt of SOP at 9.03 kg/m3

Goldphyre's Executive Chairman, Matt Shackleton commented, "The June Quarter has been very successful for our team. We have established a real, extractable, high-grade sulphate of potash Resource that sits in the palaeochannel. The Lake Wells Potash Project continues to deliver highly favourable outcomes as we de-risk the project.

Importantly, we believe our deposit is best positioned to be the first to development through the targeting of low cost and achievable sized operations."

Key Advantages of the Lake Wells Potash Project

- Ideally located closest to logistics solution, which is vital for a bulk project

- Simple, tried and common bore field brine abstraction method proposed, without the need for the more expensive, larger footprint trenching requirement

- High-grade core to the Resource located close to proposed evaporation pond sites

- Highly conducive sediment lithologies, with test-production bore pumping trial to commence (see link below)

- High demand, high value premium fertiliser product (SOP), with strong incentive to capture the import replacement and first to market opportunity currently existing in Australia

- Strong, supportive and highly experienced shareholder base in complete alignment with management's strategy to exploit all options in ensuring the Lake Wells Potash Project is developed quickly and at the most efficient CAPEX spend

Mineral Resource Estimate

In compliance with internationally recognised reporting standards that include a brine standard, Goldphyre has reported its Resource estimate using specific yield, or drainable porosity. The Company believes this is an accurate estimate of the amount of brine that can be abstracted from the aquifers.

Goldphyre has also reported its Resource estimate using total porosity, which estimates the total amount of in-situ brine in the aquifer. This allows investors to more easily make a comparison between Goldphyre's Resource estimate and estimates made by companies that choose not to disclose their resource estimates using specific yield.

The Mineral Resource (JORC 2012 Code compliant), which has been measured taking into account potential future economic abstraction, has been classified as Inferred (Table 1, Figure 1 in link below) and is estimated at 18.4 Mt at 8050 mg/L (8.050 kg/m3) Sulphate of Potash ('SOP'). A high-grade zone occupying the western part of the Lake Wells Potash Project ('LWPP'), defined as the 'Western High Grade Zone' has an Inferred estimate of 10.5 Mt at 9028 mg/L (9.028 kg/m3) SOP.

Next Steps

Aquifer Testing

Four (4) test-production bores are planned at two sites, A and B as shown in Figure 2 in link below.

The installation of the simple, low-cost test production bores will be followed by test pumping, with the aim of confirming Lake Wells' status as WA's leading potash project, building on its superior high-grade Resource and close proximity to infrastructure.

The four test-production bores will be installed at two sites, with a shallow bore into the upper aquifer and a deeper bore into the basal aquifer at each site. The Company is reviewing consultant proposals to conduct the test-pumping program, scheduled to commence upon the completion of the bore installation program, with results expected in the December quarter.

Corporate

Equity

During the quarter the Company settled the Sale and Split Commodity transaction with the Mark Creasy controlled Lake Wells Exploration Pty Ltd, by the issue of 29m ordinary shares and options over a further 6.86m ordinary shares, exercisable in two equal tranches at 10c and 15c.

In addition, 1.7m listed options (GPHO) were exercised during the quarter, raising $136,000.

Cash

At the end of the quarter, the Company had cash balances of $495,173. Subsequent to quarter end, the Company received a GST refund of $344,686, and a further $267,600 has been received through the exercise of options. Total funds received after 30 June 2016 to the date of this report is $612,286.

In addition to the above, the Company is preparing an application under the Federal Governments R&D Tax Incentive Scheme, which will be lodged in August.

To view the full report, please visit:
http://abnnewswire.net/lnk/4B5D7UAL


About Australian Potash Ltd

Goldphyre Resources Ltd ASX:GPH

Australian Potash Limited (ASX:APC) is an ASX-listed Sulphate of Potash (SOP) developer. The Company holds a 100% interest in the Lake Wells Potash Project located approximately 500kms northeast of Kalgoorlie, in Western Australia's Eastern Goldfields.

Following the release of a Scoping Study in 2017, APC has been conducting a Definitive Feasibility Study (DFS) into the development of the Lake Wells Potash Project. The Company is aiming to release the findings of the DFS in H2 2019.

The Lake Wells Potash Project is a palaeochannel brine hosted sulphate of potash project. Palaeochannel bore fields supply large volumes of brine to many existing mining operations throughout Western Australia, and this technique is a well understood and proven method for extracting brine. APC will use this technically low-risk and commonly used brine extraction model to further develop a bore-field into the palaeochannel hosting the Lake Wells SOP resource.

A Scoping Study on the Lake Wells Potash Project was completed and released on 23 March 2017. The Scoping Study exceeded expectations and confirmed that the Project's economic and technical aspects are all exceptionally strong, and highlights APC's potential to become a significant long-life, low capital and high margin sulphate of potash (SOP) producer.

https://twitter.com/OzPotash abnnewswire.com 


Contact

Matt Shackleton
Executive Chairman
e: m.shackleton@goldphyre.com.au
m: +61-438-319-841

Brenton Siggs
Technical Director
e: b.siggs@goldphyre.com.au
m: +61-427-075-225