Vancouver, Aug 16, 2013 AEST (ABN Newswire) - Coalspur Mines Limited ("Coalspur" or "Company") (googlechartASX:CPL) googlechartTSE:CPT) is able to report further progress on its application for regulatory approval of the Vista project ("Vista") in Alberta, Canada. Coalspur has received a formal notice of hearing from the Alberta Energy Regulator (the "AER"), which effectively confirms that Vista is in the final stages of the application review process. Coalspur expects this to be the final step prior to the AER issuing the licences necessary for the development of Vista.

The AER has been able to issue this notice because all technical and environmental matters pertaining to Vista have been satisfactorily dealt with. Following a final review in late September, the AER will decide whether a hearing will be set down to resolve any outstanding concerns. The Company is actively engaged with the AER to complete the application process under the new regulations, which have been in effect since 17 June 2013.

Coalspur has undertaken extensive stakeholder engagement over the last two years with all parties that could be impacted by Vista. As a result of this engagement, there is strong community support for Vista, and the Company has reached agreement with a number of potentially impacted parties and been able to reduce the Statements of Concern ("SOC") lodged with the AER down to seven active SOCs. Coalspur continues to engage with parties that it believes may be legitimately impacted by Vista and is confident that its discussions will be concluded within the timeframe stipulated by the AER.

Coalspur also notes that Canadian National Railway Company ("CN") has received final approval from the Canadian Transportation Agency for construction of the planned rail line which will provide CN with access to Vista's loading site.

Coalspur's President and CEO, Gill Winckler commented: "This notification from the AER confirms that the regulatory process for Vista is now in its final stages. We are working with the AER and their revised approval process and hope to resolve the outstanding issues in a timely manner. We are disappointed that construction on Vista will not be able to commence in September 2013 as previously expected, however, our development schedule includes numerous contingencies which will allow us to maintain the capital budget and achieve first production from Vista in mid-2015 as planned, assuming that we begin construction later this year."

About Coalspur Mines Limited

Coalspur Mines Limited (ASX:CPL)Coalspur Mines Limited (ASX:CPL) (TSE:CPT) is a coal development company with approximately 55,000 hectares of coal leases located within the Hinton region of Alberta, Canada. Coalspur's flagship project is Vista, which covers approximately 10,000 hectares and provides a large scale, surface mineable, thermal coal development. Vista is located adjacent to CN Rail's main line, which is suitable for the transport of coal to deepwater ports on Canada's west coast. Coalspur has secured a port allocation agreement with Ridley Terminals Inc., which is essential to the logistics supply chain necessary to export coal from Vista to the growing demand from the Asia Pacific countries.

abnnewswire.com 


Contact

Greg Bittar
VP, Investor Relations
Australasia
Email: gbittar@coalspur.com
P: +61-409-611-744

Chris Borowski
Investor Relations
North America and Europe
Email: cborowski@coalspur.com
P: +1-403-973-5607

David Montpetit
VP, External Affairs and Logistics
Email: dmontpetit@coalspur.com
P: +1-403-801-1344



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 9) (Last 30 Days: 31) (Since Published: 3741)