Hastings Technology Metals Ltd Stock Market Press Releases and Company Profile

View in Other Languages Hastings Technology Metals Ltd (ASX:HAS) 季度活动报告 Hastings Technology Metals Ltd (ASX:HAS) Quarterly Activities Report Hastings Technology Metals Ltd (ASX:HAS) 季度活動報告 
Quarterly Activities Report
Quarterly Activities Report

Sydney, Jan 31, 2019 AEST (ABN Newswire) - Hastings Technology Metals Ltd (googlechartASX:HAS) provides the Company's Quarterly Activities Report.

- Probable Ore Reserves increased to 10.35 million tonnes at 1.22%TREO including 0.43%Nd2O3+Pr6O11

- Updated Ore Reserves confirm >10-year mine life

- Total JORC Resources increased to 21.67 million tonnes at 1.17%TREO including 0.39%Nd2O3+Pr6O11 of which 62% are in the Measured and Indicated categories

- Successful completion of the second beneficiation pilot plant operation test. Upgrading of the Nd2O3+Pr6O11 head grade by 20 times from 0.43% to 8.6% was achieved

- EPA approval documentation was advertised to the public with an overall positive response received

To view the full report, please visit:
http://abnnewswire.net/lnk/XS3CCDZD


About Hastings Technology Metals Ltd

Hastings Technology Metals Ltd (ASX:HAS) (FRA:5AM) is advancing its Yangibana Rare Earths Project in the Upper Gascoyne Region of Western Australia towards production. The proposed beneficiation and hydro metallurgy processing plant will treat rare earths deposits, predominantly monazite, hosting high neodymium and praseodymium contents to produce a mixed rare earths carbonate that will be further refined into individual rare earth oxides at processing plants overseas.

Neodymium and praseodymium are vital components in the manufacture of permanent magnets which is used in a wide and expanding range of advanced and high-tech products including electric vehicles, wind turbines, robotics, medical applications and others. Hastings aims to become the next significant producer of neodymium and praseodymium outside of China.

Hastings holds 100% interest in the most significant deposits within the overall project, and 70% interest in additional deposits that will be developed at a later date, all held under Mining Leases. Numerous prospects have been identified warranting detailed exploration to further extend the life of the project.

Brockman Project

The Brockman deposit, near Halls Creek in Western Australia, contains JORC Indicated and Inferred Mineral Resources, estimated using the guidelines of JORC Code (2012 Edition).

The Company is also progressing a Mining Lease application over the Brockman Rare Earths and Rare Metals Project.

Hastings aims to capitalise on the strong demand for critical rare earths created by the expanding demand for new technology products.

abnnewswire.com 


Contact

Charles Lew
Chairman
T: +65-9790-9008 / +61-8-6117-6118

Andrew Reid
Chief Operations Officer
T: +61-8-6117-6118 / +61-432-740-975



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 25) (Last 30 Days: 68) (Since Published: 5905) 

View in Other Languages 628659055286 (17477)

googlechart